Tab/Accordion Items

Description: Streambank and Shoreline Protection means the use of vegetation to stabilize and protect banks of streams, lakes, estuaries, or excavated channels against scour and erosion.  This practice should be used to prevent the loss of land or damage to utilities, roads, buildings, or other facilities adjacent to the banks, to maintain the capacity of the channel, to control channel meander that would adversely affect downstream facilities, to reduce sediment load causing downstream damages and pollution, or to improve the stream for recreation or fish and wildlife habitat.

Streambank and Shoreline Protection Policy
Requirements for all Sediment and Nutrient Management Measures.
General Policies for Commission Cost Share Programs

Maintenance Period: 10 years

Additional Spot Check Requirements: None

BMP Units: Lin Ft
Cost Information: Average cost (75% or 90%). Refer to ACSP Average Cost Lists for details.

CS2 Project Description examples

Expected Results: 
Acres affected - (treated area and buffer)
Soil saved - (Estimates of streambank/shoreline erosion in tons/yr. May be substituted for soil loss calculations)

Reference Materials: 
NC-ACSP-11 Signature Page
Map with BMP location, fields, and roads
For 90% Cost share, please upload the NC-CSPs-1E form.

CS2 Common ComponentsUnits
EARTH FILL HAULEDCuYd
EXCAVATION - w/spoil removalCuYd
FILTER CLOTH - Geotextile fabricSqYd
GRADING - extra heavy, 9" - 12" avgAcre
GRADING - heavy, 6" - 9" avgAcre
GRADING - medium, <=6" avgAcre
GRADING - maximum heavy >12" avgAcre
GRADING - minimum, <= 1/4 acreAcre
VEGETATION - bag lime, seed and fertilizerAcre
VEGETATION - establish, native species for riparian areas onlyAcre
VEGETATION - HydroseedAcre
VEGETATION - Livestakes (installed)Each
VEGETATION - seedbed prepAcre
VEGETATION - mulch, small grain strawAcre
VEGETATION - Tree/Shrub Bare Root SeedlingsEach
EROSION CONTROL MATTING - TEMP, 12 MONTHS, or less LONGEVITYSqYd
EROSION CONTROL MATTING - TEMP, 18 - 36 MONTHS LONGEVITYSqYd
EROSION CONTROL MATTING - TEMP, <400 SQ FT, STRAW - 12 MONTHS or less LONGEVITYSqFt
PIPE FITTING - Corrugated PolyethyleneEach
PIPE FITTING - Polyvinyl ChlorideEach
PIPE FITTING - stormwaterEach
PIPE - CORRUGATED STORMWATER, TYPE S, SMOOTH WALL,various sizes - includes excavation and backfillLinFt
PIPE - CORRUGATED PLASTIC, polyethylene, double wall, various sizes - does not include excavationLinFt
PIPE - Polyvinyl Chloride - various sizes (does not include excavation)LinFt
STONE - Boulders (installed)Ton
STONE - gravelTon
STONE - riprapTon