Description: The use of plants and soils for removal of pollutants from stormwater runoff. Bioretention can also be effective in reducing peak runoff rates, runoff volumes and recharging groundwater by infiltrating runoff.
CCAP Bioretention Area Policy
Requirements for all CCAP practices
Maintenance Period: 5 years single-family home, 10 years all other properties.
Additional Spot Check Requirements: None
BMP Units: Square Feet
Cost Information: Actual cost - paid based on receipts. See CCAP Average Cost List for details.
CS2 Project Description examples
Expected Results:
- Total Nitrogen Removed
- Total Phosphorus Removed
- Total Suspended Solids Removed
Reference Materials:
NC-CCAP 11 Signature Page
Map with BMP location, fields, and roads
For RFP:
Receipts for actual cost items
CS2 Common Components | Units |
---|---|
CCAP - Bioretention areas - engineering | Job |
JAA:
Requires a Professional Engineer stamped design.